Upcoming Schuylkill County Road Work from PennDOT


Upcoming Scheduled Road Work from PennDOT

​Reporting unit: Bridge (Inspection)
Municipality: Butler Township
Road name: Highridge Park Road
Between: Keystone Boulevard And: Airport Road
Type of work: Inspection
Work being done by: PennDOT Bridge Inspection Forces
Type of restriction: Daytime
Restriction: Northbound right travel from 9am - 12pm
Northbound left lane from 12pm - 3pm
Southbound right travel from 9am - 3pm
Start date: 8/23/2018
Est completion date: 8/23/2018
Restrictions in effect (time of day): 9:00AM To: 3:00PM
Will rain cause delays?: Yes
Change/Update: Northbound inspection rescheduled for August 23, 2018 due to a rain event.

---------------------------------------------------------

Reporting unit: Maintenance
Municipality: East Brunswick / West Penn Townships
Road name: PA 895 / PA 443
Between: New Ringgold And: PA 309
Type of work: Other
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane closure with flagging.
Start date: 8/6/2018
Est completion date: 8/10/2018
Restrictions in effect (time of day): 7:00AM To: 3:00PM
Will rain cause delays?: No
Change/Update: Tar and Chip

---------------------------------------------------------

Reporting unit: Maintenance
Municipality: Butler Township
Road name: PA 61
Between: Frackville And: Fountain Springs
Type of work: Drainage
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 8/6/2018
Est completion date: 8/10/2018
Restrictions in effect (time of day): 7:00AM To: 3:00PM
Will rain cause delays?: No
Change/Update:

---------------------------------------------------------

Reporting unit: Maintenance
Municipality: Kline Township
Road name: PA 309
Between: McAdoo And: Hometown
Type of work: Pothole Patching
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 8/6/2018
Est completion date: 8/10/2018
Restrictions in effect (time of day): 7:00AM To: 3:00PM
Will rain cause delays?: No
Change/Update:

---------------------------------------------------------

Reporting unit: Maintenance
Municipality: Foster / Butler Townships
Road name: Interstate 81
Between: Exit 116 And: Exit 124
Type of work: Pothole Patching
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane closure northbound and southbound, be alert and anticipate delays.
Start date: 8/6/2018
Est completion date: 8/9/2018
Restrictions in effect (time of day): 7:00AM To: 3:00PM
Will rain cause delays?: No
Change/Update:

---------------------------------------------------------

Reporting unit: Maintenance
Municipality: West Mahanoy Township
Road name: PA 54
Between: Lost Creek And: Shenandoah
Type of work: Drainage
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 8/6/2018
Est completion date: 8/10/2018
Restrictions in effect (time of day): 7:00AM To: 3:00PM
Will rain cause delays?: No
Change/Update:

---------------------------------------------------------

Reporting unit: Bridge (Inspection)
Municipality: Fraily Township
Road name: Interstate 81
Between: US 209 (Exit 107) And: PA 25 (Exit 112)
Type of work: Inspection
Work being done by: PennDOT Bridge Inspection Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging on southbound right lane.
Start date: 8/6/2018
Est completion date: 8/7/2018
Restrictions in effect (time of day): 9:00PM To: 3:00PM
Will rain cause delays?: Yes
Change/Update:

---------------------------------------------------------

Reporting unit: Bridge (Inspection)
Municipality: Kline Township
Road name: Interstate 81 Northbound
Between: Exit 134 And: Exit 141
Type of work: Inspection
Work being done by: PennDOT Bridge Inspection Forces
Type of restriction: Daytime
Restriction: Northbound Right Lane Restriction. Flaggers are needed underneath while doing the span over SR 8017
Start date: 8/8/2018
Est completion date: 8/8/2018
Restrictions in effect (time of day): 9:00AM To: 3:00PM
Will rain cause delays?: Yes
Change/Update:

---------------------------------------------------------

Reporting unit: Bridge (Inspection)
Municipality: Kline Township
Road name: PA 309 South Ramp
Between: Interstate 81 Exit 138 And: PA 309
Type of work: Inspection
Work being done by: PennDOT Bridge Inspection Forces
Type of restriction: Daytime
Restriction: Northbound Left Lane Restriction.
Start date: 8/9/2018
Est completion date: 8/9/2018
Restrictions in effect (time of day): 9:00AM To: 3:00PM
Will rain cause delays?: Yes
Change/Update:

---------------------------------------------------------

Reporting unit: Maintenance
Municipality: Porter / Foster / Pine Grove Townships
Road name: Interstate 81
Between: Exit 107 And: Lebanon County Line
Type of work: Other
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane closure northbound and southbound, be alert and anticipate delays.
Start date: 8/6/2018
Est completion date: 8/9/2018
Restrictions in effect (time of day): 7:00AM To: 3:00PM
Will rain cause delays?: No
Change/Update: Storm Damage Restoration